CONTEXT
The project aims to modify the process of the INVISTA production plant, operated by BUTACHIME and located on the SOLVAY site in Chalampé.
SOLUTIONS
The project includes :
- The construction of two new units: Mixing Unit / Tank Farm.
- Modification of the existing units: Distillation / Tank farm
- The extension of the interconnection racks.
The overall type of work carried out is as follows:
- Piping works (detail design, prefabrication, on-site erection, on-site inspection and testing, project documentation)
- Mechanical assembly of equipment and packaging,
- Insulation and painting.